August 2022 Project Update

After waiting over 8-12 weeks on back orders and delivery issues, we finally received the remaining block on order so that we could finish the vast majority of the retaining wall construction allowing for the extension outward of the top back patio and putting green areas. 

August Update

The pictures below show the before and after, and how extensive the retaining wall construction extends around the periphery of the clubhouse hill and sloping areas, encompassing this whole area. 

BEFORE

AFTER

Now with these retaining walls finally in place this will allow us over the next weeks to obtain the necessary permitting, finish final grading, install irrigation, lighting, pour concrete and lay sod in order to complete this area for public use. 